澳大利亚it作业:Individual case study 个案研究 [5]
论文作者:留学生论文论文属性:案例分析 Case Study登出时间:2013-12-13编辑:anne点击率:12910
论文字数:3350论文编号:org201312130917375487语种:英语 English地区:澳大利亚价格:免费论文
关键词:澳大利亚it作业Individual case study个案研究
摘要:案例研究模拟了一个项目管理方案,其中学生需要在项目经理的角色。此案的资料不完整,以便在有需要的学生将不得不做出的假设和/或从他们的导师/讲师那里得到帮助。
tting up of database queries. The following timings were estimated:
Report Program X:
2 weeks
Report Program Y:
3 weeks
Report Program Z:
1 week
Queries:
2 weeks
Assume that work could not commence on the customised reporting programs until testing was complete for all the conversion programs (A, B and C).
The Council decided that it wanted the ratepayers to be aware of the introduction of the new system, particularly the introduction of water meters. Accordingly, it arranged for an advertising agency to carry out the following:
Telecom hot line installation – allow 1 day to complete. To be completed 2 weeks before "systems go" Brochures design/print – allow 8 weeks to complete. To be completed 6 weeks before "systems go" Newspaper art work. - allow 2 weeks to complete. To be completed to allow insertion in newspaper 4 weeks before "systems go".
Assumptions
Assume that the project commences with the appointment of the Council strategic committee and that this date is 1st July 2013. Assume there are no public holidays between July and late December, but from 25 December until end January 2014 (31/1/14) all staff will be on annual leave. Project staff will normally work five (5) days per week, eight (8) hours per day. The software house has four staff available for the project. You must also allocate the contractor resources to the tasks on your schedule as part of this assignment.
Part A Requirements and Questions
For part A of the assessment you must complete the following tasks and questions. Read all the questions before you commence the tasks. The schedule is to be developed in an appropriately named Microsoft Project 2010 file (e.g. WaterMeters-PartA.mpp) and the questions are to be answered in a Word document. Any assumptions must also be listed at the beginning of the Word document.
1. Based on the information in the case study description above, use the Microsoft Project 2010 software to produce a Part A project schedule. You should be mindful of the marking criteria and ensure that activities described in the case are included and sequenced correctly with all resource and duration information. Any resource over-allocation issues must be resolved in your schedule without the addition of extra resources. The schedule is to show all activities from 1/7/13 until the system “goes live”. You should organise your tasks into key work packages (summary tasks) with sub-tasks (and sub-summary tasks etc.).
One way to organise the WBS is according to the following summary tasks:
Rockstone Water Meters
Pre Project Manager Appointment Tasks (committee deliberaation and PM appointment etc.)
:
DataBase Training (arrangement and actual training)
:
Portable Data Entry system
:
Water Meters
:
Revenue System
:
Awareness Campaign
:
<